Orlando Stormwater Infrastructure Projects, Funding and Design
Orlando's stormwater program combines a dedicated utility fee with a defined capital pipeline for drainage, rehabilitation and water-quality work. The City's stormwater capital schedule totals about $88.75 million across FY2023/24-FY2027/28. Colonialtown Phase 3 carries $6 million and is at 60% design, while Colonial Phase 4 is in design with $2.7 million programmed. The Streets and Stormwater Division also operates and maintains more than 800 miles of roadways and rights-of-way together with the city's drainage system.
Orlando Stormwater Capital Program and Design Activity
How Orlando Stormwater Projects Move from Funding to Delivery
Orlando Stormwater Owners and Delivery Paths
Orlando Stormwater Infrastructure Project Intelligence
Related Markets
Track Orlando Stormwater Projects from Funding Through Delivery
Commercial Signals and Market Development
For firms serving stormwater assets, the program provides a durable account view while individual project pages establish the scope and timing of specific opportunities.
That stage provides time to understand the project team and technical scope from public information before a construction package reaches formal procurement.
Separating these project types helps teams focus account coverage on the asset classes and technical capabilities that match their offering.
PROJECT INTELLIGENCE FAQ
Frequently Asked Questions
How much stormwater capital work is programmed in Orlando?
The City's published stormwater project schedule totals approximately $88.75 million across FY2023/24 through FY2027/28.
How much stormwater capital work is programmed in Orlando?
The City’s published stormwater project schedule totals approximately $88.75 million across FY2023/24 through FY2027/28.
What is the current status of Orlando's Colonialtown stormwater projects?
Colonialtown Phase 3 is at 60% design with $6 million programmed. Colonial Phase 4 is in design with $2.7 million programmed.
What is the current status of Orlando's Colonialtown stormwater projects?
Colonialtown Phase 3 is at 60% design with $6 million programmed. Colonial Phase 4 is in design with $2.7 million programmed.
Which City department manages Orlando stormwater infrastructure?
The City of Orlando Streets and Stormwater Division operates and maintains the municipal drainage system, including stormwater pipes, canals and retention ponds, and also maintains more than 800 miles of roadways and rights-of-way.
Which City department manages Orlando stormwater infrastructure?
The City of Orlando Streets and Stormwater Division operates and maintains the municipal drainage system, including stormwater pipes, canals and retention ponds, and also maintains more than 800 miles of roadways and rights-of-way.
Sources and Methodology
Sources & Intelligence Methodology
Market and geographic context on this page is informed by official plans, budgets, capital programs, board materials, public records, and other government or public-owner sources. The early-stage project signals and pre-RFP opportunity previews are provided separately through Citylitics’ proprietary sales intelligence platform, which continuously identifies and tracks infrastructure opportunities as they develop toward procurement.
City of Orlando Streets and Stormwater Division | Current
Lists Orlando’s stormwater utility fee schedule and stormwater capital projects, including programmed costs and current project phases.
City of Orlando | Current
Describes the City division responsible for more than 800 miles of roadways and rights-of-way, drainage systems, stormwater pipes, canals, retention ponds and lake-water-quality monitoring.
City of Orlando | 2026
Lists the $1.3 million Lake Arnold stormwater and water-quality pilot, with anticipated construction from fall 2026 through summer 2027.
TL;DR
Orlando's published stormwater capital schedule totals about $88.75 million across FY2023/24-FY2027/28.
Colonialtown Phase 3 is at 60% design with $6 million programmed, while Colonial Phase 4 is in design with $2.7 million.
The Streets and Stormwater Division maintains Orlando's drainage system alongside more than 800 miles of roadways and rights-of-way.