Woodstock, IL Public Infrastructure Projects and Capital Programs
Woodstock, IL public infrastructure projects are supported by a current ten-year Capital Improvement Program and an active regional construction project. The City's FY 2026-27 through FY 2035-36 CIP totals $196.6 million, including $58.4 million for water and sewer and $53.3 million for streets, sidewalks, signals, and stormwater. Separately, the Route 47 Widening and Expansion represents an estimated $78.4 million total investment. The construction contract is awarded to Berger Excavating, and the City announced that active construction would begin the week of April 1, 2026 after utility relocation work.
Woodstock Public Infrastructure: A $196.6M CIP and Active Route 47 Construction
How Woodstock Moves From Ten-Year Planning to Active Construction
A Forward Municipal CIP Behind an Active Regional Construction Program
Developing Public Infrastructure Activity in Woodstock
Similar Regions in This Market
Citylitics Market Development Platform for Woodstock Public Infrastructure
Upcoming Commercial Signal in Woodstock's Ten-Year CIP
PROJECT INTELLIGENCE FAQ
Frequently Asked Questions
How large is Woodstock's current ten-year Capital Improvement Program?
The City's FY 2026-27 through FY 2035-36 CIP totals $196.6 million. Water and sewer account for $58.4 million, while streets, sidewalks, signals and stormwater account for $53.3 million.
How large is Woodstock's current ten-year Capital Improvement Program?
The City’s FY 2026-27 through FY 2035-36 CIP totals $196.6 million. Water and sewer account for $58.4 million, while streets, sidewalks, signals and stormwater account for $53.3 million.
What stage is the Route 47 Widening Project in?
The City states that the contract was awarded to Berger Excavating following the April 25, 2025 bid opening and documents the corridor as an awarded construction program. Route 47 is therefore delivery-stage context and the original prime contract has already been awarded.
What stage is the Route 47 Widening Project in?
The City states that the contract was awarded to Berger Excavating following the April 25, 2025 bid opening and documents the corridor as an awarded construction program. Route 47 is therefore delivery-stage context and the original prime contract has already been awarded.
What document defines Woodstock's forward municipal infrastructure pipeline?
The FY 2026-27 through FY 2035-36 Capital Improvement Program is the forward municipal pipeline. It identifies planned spending across water and sewer, streets and stormwater, facilities, parks and other capital categories, with later engineering, bid and award records establishing project-specific procurement.
What document defines Woodstock's forward municipal infrastructure pipeline?
The FY 2026-27 through FY 2035-36 Capital Improvement Program is the forward municipal pipeline. It identifies planned spending across water and sewer, streets and stormwater, facilities, parks and other capital categories, with later engineering, bid and award records establishing project-specific procurement.
Sources and Methodology
Sources & Intelligence Methodology
Market and geographic context on this page is informed by official plans, budgets, capital programs, board materials, public records, and other government or public-owner sources. The early-stage project signals and pre-RFP opportunity previews are provided separately through Citylitics’ proprietary sales intelligence platform, which continuously identifies and tracks infrastructure opportunities as they develop toward procurement.
City of Woodstock, Illinois | 2026-01-20
Current City ten-year CIP documenting $196.6 million in planned expenditures and the major water/sewer and streets/sidewalks/signals/stormwater categories.
City of Woodstock, Illinois | 2026-02-11
Official City release documenting the estimated $78.4 million Route 47 investment, the City share, and the $15.65 million outside funding stack.
City of Woodstock, Illinois | Accessed 2026-10-15
Official City project overview documenting the Route 47 award to Berger Excavating, the 2.25-mile widening scope, water and sewer main work, project funding and the multi-year construction program.
TL;DR
Woodstock's FY 2026-27 through FY 2035-36 Capital Improvement Program totals $196.6 million, including $58.4 million for water and sewer and $53.3 million for streets, sidewalks, signals, and stormwater.
The Route 47 Widening and Expansion represents an estimated $78.4 million total investment, with $15.65 million in outside funding supporting the City's portion of the project.
Route 47 is no longer an upcoming prime bid: Berger Excavating holds the construction contract, and the City announced active construction beginning in April 2026 after utility relocation.