Urbandale, IA Public Infrastructure Projects: Capital Plans and Procurement Stages
Urbandale IA public infrastructure projects include a city CIP, a voter-approved police-station bond, a closed water-well tender and later WRA sewer phases.
Urbandale IA public infrastructure projects: plans, bids and construction
The Infrastructure Project Lifecycle
Three owners and three distinct contracting paths
Live Urbandale infrastructure project signals
Similar Regions in This Market
Citylitics: Urbandale Infrastructure Project Coverage
Commercial Signals: Planned City and Regional Work
PROJECT INTELLIGENCE FAQ
Frequently Asked Questions
Who owns Urbandale infrastructure projects?
The City manages municipal streets, facilities, and stormwater. Urbandale Water Utility runs its own water procurement. The metropolitan Wastewater Reclamation Authority controls the regional Joint and Common Trunk Sewer program.
Who owns Urbandale infrastructure projects?
The City manages municipal streets, facilities, and stormwater. Urbandale Water Utility runs its own water procurement. The metropolitan Wastewater Reclamation Authority controls the regional Joint and Common Trunk Sewer program.
Which Urbandale projects are still at a planning or design stage?
The adopted City CIP contains proposed projects subject to later approvals, while the police station is in design and construction planning following its November 3, 2026 bond vote. Check subsequent Council decisions for procurement packages.
Which Urbandale projects are still at a planning or design stage?
The adopted City CIP contains proposed projects subject to later approvals, while the police station is in design and construction planning following its November 3, 2026 bond vote. Check subsequent Council decisions for procurement packages.
Can contractors still bid on the 170th Street ASR well construction contract?
Not under the cited Contract 1-2026 tender: Urbandale Water Utility lists October 27, 2026 as the bid deadline, with Board consideration scheduled for November 10. Monitor official utility notices for further packages or changes.
Can contractors still bid on the 170th Street ASR well construction contract?
Not under the cited Contract 1-2026 tender: Urbandale Water Utility lists October 27, 2026 as the bid deadline, with Board consideration scheduled for November 10. Monitor official utility notices for further packages or changes.
What is the next phase of the WRA trunk sewer?
The WRA schedules Phase 1 construction for 2026-2027, Phase 2 for 2027-2028 and Phase 3 for 2029-2030. Those schedules indicate planned work, but any procurement must be confirmed directly with WRA.
What is the next phase of the WRA trunk sewer?
The WRA schedules Phase 1 construction for 2026-2027, Phase 2 for 2027-2028 and Phase 3 for 2029-2030. Those schedules indicate planned work, but any procurement must be confirmed directly with WRA.
Sources and Methodology
Sources & Intelligence Methodology
Market and geographic context on this page is informed by official plans, budgets, capital programs, board materials, public records, and other government or public-owner sources. The early-stage project signals and pre-RFP opportunity previews are provided separately through Citylitics’ proprietary sales intelligence platform, which continuously identifies and tracks infrastructure opportunities as they develop toward procurement.
City of Urbandale | November 4, 2026
City confirmation of the November 3 bond approval, estimated $60 million cost and ongoing design planning.
urbandale.org | January 6, 2026
Supports the following figures used in this analysis: $218.96M - Five-year proposed expenditures in the City’s adopted 2026-2031+ CIP; not a commitment to fund every project; $15.5M - ASR well planned amount in the City CIP; construction bids closed October 27, 2026.
urbandale.org | 2026
Supports the following figure used in this analysis: 460+ - Lane miles managed by Urbandale Engineering and Public Works.
TL;DR
Urbandale adopted its 2026-2031+ CIP in January 2026, describing approximately $218.96 million in 2026-2030 planned expenditures; CIP adoption alone is not a contract or funding guarantee.
The $60 million police station gained voter authorization for up to $25 million in bonds on November 3, 2026; results were still unofficial when the City announced them November 4.
The 170th Street ASR construction bid closed October 27, with a November 10 Board decision scheduled. WRA Joint Trunk Sewer Phase 1 is under construction, while later phases remain scheduled.