Seattle, WA Transportation Infrastructure Projects: Levy Funding, I-5 Construction and Corridor Planning
Seattle, WA transportation infrastructure projects currently span voter-approved city funding, active state construction and long-range corridor planning. Seattle's eight-year Transportation Levy provides $1.55 billion for streets, bridges, safety and transit connections. WSDOT's $178 million Revive I-5 Ship Canal Bridge project is in construction on a corridor carrying almost 240,000 vehicles per day, with major work continuing into 2027. WSDOT is also developing the I-5 Master Plan with $11.75 million in 2025-27 biennium funding and a planned 2028 publication. These records separate current delivery from longer-range planning.
Seattle Transportation Infrastructure: Levy Funding, I-5 Construction and Planning
The Infrastructure Project Lifecycle
Where Seattle Transportation Activity Is Moving
What to Watch Next in Seattle, WA Transportation Infrastructure
Similar Regions in This Market
Citylitics Intelligence for Seattle, WA Transportation Infrastructure
Current Commercial Signals in Seattle
PROJECT INTELLIGENCE FAQ
Frequently Asked Questions
What is Seattle's current Transportation Levy value?
Seattle voters approved an eight-year, $1.55 billion Transportation Levy in 2024 for street, bridge, safety, transit-connection and other transportation programs.
What is Seattle's current Transportation Levy value?
Seattle voters approved an eight-year, $1.55 billion Transportation Levy in 2024 for street, bridge, safety, transit-connection and other transportation programs.
What stage is the Revive I-5 Ship Canal Bridge project in?
The $178 million WSDOT project is in construction. Major northbound work is wrapping up in late 2026, major southbound work is planned for 2027 and completion is projected for the end of 2027.
What stage is the Revive I-5 Ship Canal Bridge project in?
The $178 million WSDOT project is in construction. Major northbound work is wrapping up in late 2026, major southbound work is planned for 2027 and completion is projected for the end of 2027.
What stage is the I-5 Master Plan in?
The Master Plan is in progress. WSDOT is developing and screening potential solutions, expects prioritization and investment-strategy work in 2027 and plans to publish the Master Plan in 2028.
What stage is the I-5 Master Plan in?
The Master Plan is in progress. WSDOT is developing and screening potential solutions, expects prioritization and investment-strategy work in 2027 and plans to publish the Master Plan in 2028.
Sources and Methodology
Sources & Intelligence Methodology
Market and geographic context on this page is informed by official plans, budgets, capital programs, board materials, public records, and other government or public-owner sources. The early-stage project signals and pre-RFP opportunity previews are provided separately through Citylitics’ proprietary sales intelligence platform, which continuously identifies and tracks infrastructure opportunities as they develop toward procurement.
Washington State Department of Transportation | 2026
Official WSDOT project page documenting active construction, $178 million funding, nearly 240,000 daily bridge vehicles and the 2026-2027 work sequence.
Washington State Department of Transportation | 2026
Official WSDOT planning page documenting the in-progress I-5 Master Plan, $11.75 million 2025-27 biennium planning budget and expected 2028 publication.
Seattle Department of Transportation | 2024-11-05
Official SDOT page documenting the voter-approved eight-year $1.55 billion Transportation Levy and its program areas.
TL;DR
Seattle's voter-approved Transportation Levy provides $1.55 billion over eight years for city transportation programs.
WSDOT's $178 million Revive I-5 Ship Canal Bridge preservation project is in construction on a bridge carrying almost 240,000 vehicles per day.
WSDOT's I-5 Master Plan remains in development with $11.75 million in 2025-27 biennium planning funding and publication expected in 2028.